Works on external walls manufacturing are started. The production of stair flights on the 7th and 8th floors is finished.
Works are finished on the 2nd-3rd-4th floors: plumbing communications laying, electrical communications works, interior partitions of apartments.
Medical tourism is developing extremely fast in Thailand. Thousands of people all over the world come here to solve healthcare…
Thailand is considered to be one of the leading golf tourism and health tourism destinations in the world. World’s largest companies…
Works are in progress: plumbing communications laying, electrical communications works, interior partitions of apartments on the 2nd-3rd-4th floors.
Works are in progress: stairs and wall columns concreting, floor slabs reinforcement, the 8th floor is built, floor cleaning of…