Construction Update November 2017

Doors have completely been installed in all units on the 2nd floor and 3rd floor. Additional doors have been delivered for further installation on other floors. The durable corridor flooring has been completed on 2nd - 7th floor. The installation of the fire exit’s stair railing has been started. The rooftop barrier is currently in progress prior to build the rooftop garden. Doors covering water waste system have already been installed on lower floors. Electrical Distribution Board, light switches, electrical sockets, and waterproof electrical sockets including Fiber Optic internet have completely been installed in all units. Electrical Main Distribution Board is delivered and ready for further progress to divide electrical power feed into subsidiary circuits.
30.11.2017