News

Construction Update January 2018

Glass windows have completely been installed on all floors and glass sheets have been continuously being installed on safety barriers around corridors of each floor. Glass windows have completely been installed on all units and glass sheets have been continuously being installed on safety barriers of each unit’s balcony. Very high-quality doors, locks, and handles are installed as every unit’s door, bedroom’s door and bathroom’s door. Built-in kitchen has continuously been being installed inside each unit on higher floors. Built-in wardrobe has continuously been being installed inside each unit on higher floors. Built-in cabinet and water system including electrical system being ready for electrical appliances have continuously been being installed inside each unit on higher floors. Final parts of ceilings, in each unit and in common walkways have continuously been being installed on higher floors. Stair tiles have completely been laid on every main stairs on all floors. Swimming pool system has almost been completed.
03.02.2018

Still have questions

AURORA team member will contact you immediately